Motorists have voiced frustration over roadworks on Blackburn Road after lane closures caused long queues and congestion stretching back towards Egerton.
The gas works are taking place on Blackburn Road near John Holden's Mill and Hill Cot Road in Sharples.
Traffic is reduced from two lanes to one in the affected area, with residents reporting significant delays in recent days.
This is particularly during busy periods, when queues have been backing up along one of Bolton's busiest routes.
Astley Bridge's Cllr Hilary Fairclough said she had received complaints from motorists.
(Image: NQ)
She said: "I went out yesterday afternoon and I noticed traffic was backed well up. It was a lovely sunny day, it was half two in the afternoon, and I didn't see anybody working.
"There was nothing but backed-up traffic. It was absolutely horrendous."
Cllr Fairclough said the congestion appeared to extend as far as Egerton at times. She feared conditions would be even worse during the morning rush hour.
She said: "I feel for people trying to get to work because it would have been horrendous. It's absolutely shocking."
The councillor has contacted those responsible for the works.
She questioned whether the traffic management arrangements could be altered to reduce disruption during peak travel times.
She said: "If they're only working on the pavements, then the actual road isn't being disrupted.
"They could move the cones until 9.30am to allow the free flow of traffic and then put them back out again."
(Image: NQ)
According to Cllr Fairclough, residents from nearby roads including Hill Cot Road are also likely to be affected by the reduced capacity on Blackburn Road.
She added: "It must be a nightmare for people trying to get out when there's just one line of traffic.
"Nobody wants to give way. It's just horrendous."
The councillor stressed that residents generally understand when essential work has to be carried out.
She said the level of disruption had raised questions.
She said: "If it's an emergency, people understand it. If it's something that has to be done, people understand it.
"But at the moment, what it looks like is they've got everything ready for whatever it is they're doing and then they've gone off on their holidays."
Chris Campbell, Customer Operations Area Manager for Cadent in the North West, said: “Our engineers began work on 4 November to repair a section of gas pipe under Blackburn Road in Bolton.
“Due to the location of the pipe being beneath the carriageway, a lane closure is in place to ensure the safety of drivers and our engineers while we complete this emergency work.
“We thank everyone for their patience, and we are working with the highways authority to manage traffic disruptions.
“If you smell gas, do not assume it is related to this work. Call the national gas emergency service immediately on 0800 111 999*.”
A Bolton Council spokesperson said: "The current works are immediate/urgent works to repair a leaking gas main.
"Works commenced on November 13; proposed end date of November 19.
"We have requested that the length of the traffic management is shortened to try and minimise the overall works footprint."